Entering Progress Data
AIA Billing

Entering Progress Data

How to enter work completed this period and materials stored

6 minLast updated: 2025-01-15
progresswork completedmaterials storedpercentagecolumns

Accurately entering progress data is crucial for getting paid correctly and on time. This guide covers best practices for entering work completed and materials stored on your pay applications.

Understanding the G703 Columns

The G703 continuation sheet tracks progress across several columns. Understanding each column helps you enter data correctly.

ColumnNameDescriptionEditable
DWork Completed - PreviousCumulative value from prior billing periodsNo (auto-calculated)
EWork Completed - This PeriodDollar value of work done this periodYes
FMaterials Presently StoredOn-site materials not yet installedYes
GTotal Completed and StoredD + E + FNo (auto-calculated)

Column Math

G = D + E + F for each line item. RIVET calculates this automatically as you enter values.

Entering Work Completed

Method 1: By Dollar Amount

The most precise method - enter the exact dollar value of work completed:

  1. Click in the "This Period" column for the line item
  2. Type the dollar amount (e.g., 5000 or $5,000)
  3. Press Tab or Enter to move to the next item

Method 2: By Percentage

Alternatively, you can enter a target percentage complete:

  1. Click the percentage toggle on the line item
  2. Enter your target completion percentage (e.g., 75%)
  3. RIVET calculates the dollar amount needed to reach that percentage

When to Use Each Method

Use dollar amounts when you have precise cost information (like installed equipment costs). Use percentages for labor-intensive items where you estimate completion visually.

Materials Stored Best Practices

What Qualifies as Materials Stored

Materials can be billed when stored if:

  • They're physically on the job site (not at your warehouse)
  • They're specifically allocated to this project
  • Your contract allows billing for stored materials
  • You can document their presence (photos, delivery tickets)

What Does NOT Qualify

  • Materials at your shop or warehouse
  • Materials ordered but not delivered
  • Tools and equipment (not consumed in the work)
  • Materials not specific to this project

Documentation Required

GCs typically require documentation for stored materials, including photos, delivery tickets, and insurance certificates. Have these ready before billing.

Moving Materials to Work Completed

When you install materials that were previously stored, the value moves from Column F to Column E:

  1. Reduce Materials Stored by the installed amount
  2. Add that amount to Work Completed This Period
  3. The Total (Column G) stays the same

Example

You have $10,000 in stored materials. You install $6,000 worth. Your next pay app shows: Materials Stored = $4,000 (reduced) and This Period includes the $6,000 (added to work completed).

Tracking Percentage Complete

The 95% Rule

Many GCs won't approve billing beyond 95% until punchlist is complete. Consider stopping at 95% completion and billing the final 5% after punchlist acceptance.

Progressive Percentages

Your percentages should always increase or stay the same - never decrease (unless work was actually removed). Example progression:

Pay AppPercentageNotes
#115%Initial work
#235%Continuing
#355%Past halfway
#475%Progressing well
#590%Near completion
#695%Awaiting punchlist
Final100%Complete

Be Realistic

Don't overbill. If the GC's field inspection shows 40% complete but you billed 60%, your pay app will be rejected and you'll lose credibility.

Entry Validation

RIVET validates your entries to catch common errors before you submit:

ValidationWhat It Checks
Over-billing PreventionTotal cannot exceed scheduled value
Negative ProgressWork completed cannot be negative
Percentage LimitsCapped at 100% per line item
Backward ProgressWarns if percentage decreases from prior period

Quick Entry Tips

Tab Navigation

Use Tab to move between fields quickly. RIVET remembers your cursor position so you can efficiently work through all line items.

Bulk Entry

If multiple items are at the same percentage, you can select them and apply a bulk percentage update.

Copy Previous Pattern

For consistent line items, you can copy the previous period's percentage increase pattern.

Common Mistakes to Avoid

  • Billing ahead of work - Never bill more than you've actually completed
  • Ignoring materials movement - Remember to move stored materials to work completed when installed
  • Inconsistent percentages - Percentages should progress logically each period
  • Missing documentation - Have backup for your progress claims ready

Next Steps

Once you've entered all your progress, review the summary and submit to your GC.

Need Help?

If you have questions about entering progress data, contact our support team at support@slpwlk.io.

Related Articles

aia billingUnderstanding AIA DocumentsAn overview of AIA G702 and G703 documents and their purpose in construction billingRead moreaia billingThe 9-Line Payment ApplicationDetailed explanation of each line in the AIA G702 payment applicationRead moreaia billingCreating a Pay ApplicationStep-by-step guide to creating a new pay application in RIVETRead more
Can't find what you're looking for?
Contact Support

Product

  • Features
  • Pricing
  • Integrations

Solutions

  • For Electricians
  • For Plumbers
  • For HVAC
  • For General Trades

Company

  • About
  • Contact
  • Security

Resources

  • Support Center
  • Templates
  • Blog

Compare

  • vs Knowify
  • vs Werx

Legal

  • Privacy Policy
  • Terms of Service
Rivet

© 2026 Rivet, Inc. All rights reserved.