Creating a pay application in RIVET is a guided process that walks you through selecting the billing period, entering progress on each line item, and generating your AIA G702/G703 documents.
Before You Start
To create a pay application, you need:
- An active project with a completed Schedule of Values
- Progress information for each line item you're billing
- Any materials stored values (if applicable)
SOV Required
Starting a New Pay Application
Follow these steps to start a new pay application:
- Navigate to your project in RIVET
- Click the Billing tab or section
- Click New Pay Application
- The Pay App Wizard will open
Available on All Plans
Step 1: Billing Period
First, define the billing period for this pay application:
Application Number
RIVET assigns the next sequential number automatically. Application #1 is your first billing, #2 is second, and so on.
Period Dates
Enter the start and end dates for this billing period. Typically this matches your billing cycle (monthly, bi-weekly, etc.).
| Field | Description |
|---|---|
| Period Start | First day of work being billed |
| Period End | Last day of work being billed |
Period Continuity
Step 2: Enter Progress
This is where you enter your progress on each Schedule of Values line item. You'll see a table with all your SOV items.
Columns You'll See
| Column | Description | Editable |
|---|---|---|
| Item # | Line item number | No |
| Description | Line item description | No |
| Scheduled Value | Contract amount for this item | No |
| Previous | Completed in prior periods | No |
| This Period | Work completed this period | Yes |
| Materials Stored | Materials on site not yet installed | Yes |
| Total | Cumulative completed + stored | Calculated |
| % Complete | Percentage of scheduled value | Calculated |
Entering Progress Values
For each line item, enter either:
- Dollar amount - The value of work completed this period (e.g., $5,000)
- Percentage - The completion percentage (RIVET calculates the dollar value)
Quick Entry
Materials Stored
If you have materials on the job site that aren't yet installed, enter them in the Materials Stored column. Common examples:
- Electrical panels delivered but not installed
- Pipe and fittings on site
- HVAC equipment staged for installation
Materials vs. Work
Step 3: Review Summary
Before generating documents, review the calculated summary. You'll see all 9 lines of the G702 with calculated values.
What to Verify
Check these values before proceeding:
| Line | What to Check |
|---|---|
| Line 4 | Does the total completed match your expectations? |
| Line 5 | Is retainage calculating correctly? |
| Line 7 | Does this match your previous pay app? |
| Line 8 | Is this the payment amount you expect? |
Step 4: Generate Documents
Once you're satisfied with the summary, click Generate Pay Application. RIVET creates:
- AIA G702 - The summary payment application
- AIA G703 - The continuation sheet(s) with line item details
- Combined PDF - Both documents in a single file
Download Options
| Format | Best For |
|---|---|
| Printing and email submission | |
| Excel | When GC requires spreadsheet format |
Editing a Pay Application
You can edit a pay application as long as it's still in Draft status:
- Open the pay application from the billing list
- Click Edit
- Update your progress values
- Regenerate documents
Submitted Applications
Quick Tips
Check Before Submit
Consistent Percentages
Save as Draft
Next Steps
Continue learning about pay applications:
- Entering progress data - Best practices for accurate billing
- Submitting to your GC - How to send your pay application
- Pay app status lifecycle - Track your applications through approval
Need Help?