Retainage
How Retainage is Calculated
Retainage

How Retainage is Calculated

Learn how RIVET calculates retainage on work completed and materials stored

5 minLast updated: 2025-01-15
calculationpercentageformulawork completedmaterials

RIVET calculates retainage automatically based on your project settings. Understanding the calculation helps you verify amounts and explain retainage to your team.

Pro Feature Required

Retainage tracking is available on Pro and Scale plans only. Starter plan does not include retainage features. Upgrade your plan in Settings to access retainage tracking and calculations.

Basic Retainage Formula

At its simplest, retainage is calculated as:

Retainage = Total Completed × Retainage Rate

Example

Total Completed and Stored$250,000
Retainage Rate10%
Retainage Amount$25,000

AIA G702 Line 5 Calculation

On the AIA G702, retainage appears in Line 5. This is the cumulative retainage on all work completed and materials stored to date (Line 4).

LineDescriptionAmount
Line 4Total Completed and Stored to Date$250,000
Line 5Retainage (10%)$25,000
Line 6Total Earned Less Retainage$225,000

Cumulative Calculation

Line 5 shows the total retainage held, not just retainage on this period's work. It's calculated on the cumulative Line 4 value.

Different Rates for Work vs. Materials

Some contracts have different retainage rates for work completed versusmaterials stored. RIVET supports this:

Example: 10% on Work, 5% on Materials

CategoryAmountRateRetainage
Work Completed$200,00010%$20,000
Materials Stored$50,0005%$2,500
Total$250,000-$22,500

Reduced Retainage After 50%

When your contract allows reduced retainage after reaching a milestone (typically 50%), the calculation becomes more complex.

How It Works

  1. Calculate retainage on work before the threshold at the original rate
  2. Calculate retainage on work after the threshold at the reduced rate
  3. Sum both amounts for total retainage

Example: 10% Reducing to 5% at 50%

On a $500,000 contract at 60% complete ($300,000):

PortionAmountRateRetainage
First 50% ($250,000)$250,00010%$25,000
Next 10% ($50,000)$50,0005%$2,500
Total$300,000-$27,500

Effective Rate

Notice the effective retainage rate is 9.17% ($27,500 / $300,000), not a flat 10% or 5%. This blended approach is correct.

Per-Line Item Retainage

On the G703, Column J shows retainage for each line item. RIVET calculates this using the same rules, applied per line:

ItemTotal (Col G)% CompleteRetainage (Col J)
Rough-in Electrical$50,000100%$5,000
Panel Installation$30,00075%$3,000
Finish Trim$10,00025%$1,000
Total$90,000-$9,000

Configuring Retainage in RIVET

Project Settings

Set up retainage when creating a project or in project settings:

  1. Navigate to your project
  2. Open Settings
  3. Find the Retainage section
  4. Configure your rates and rules

Available Options

  • Retainage Rate - Primary rate (e.g., 10%)
  • Materials Rate - Rate for stored materials (if different)
  • Reduced Rate - Rate after threshold (e.g., 5%)
  • Threshold - When reduced rate applies (e.g., 50%)

Set Early

Configure retainage settings before creating your first pay application. Changing settings later may require recalculation of previous applications.

Common Calculation Issues

Rounding Differences

Manual calculations often have small rounding differences from RIVET. RIVET uses precise decimal calculations and rounds only in the final display.

Materials Not Included

If your retainage seems low, verify whether materials stored are being included in the calculation per your contract.

Reduced Rate Not Applied

If you've passed 50% but still see the full rate, check that reduced retainage is configured in your project settings.

Next Steps

  • Learn about the release process
  • See how retainage syncs to accounting

Need Help?

If you have questions about retainage calculations or need assistance, contact our support team at support@slpwlk.io.

Related Articles

aia billingThe 9-Line Payment ApplicationDetailed explanation of each line in the AIA G702 payment applicationRead moreaia billingEntering Progress DataHow to enter work completed this period and materials storedRead moreretainageWhat is Retainage?Understanding retainage in construction and why it mattersRead more
Can't find what you're looking for?
Contact Support

Product

  • Features
  • Pricing
  • Integrations

Solutions

  • For Electricians
  • For Plumbers
  • For HVAC
  • For General Trades

Company

  • About
  • Contact
  • Security

Resources

  • Support Center
  • Templates
  • Blog

Compare

  • vs Knowify
  • vs Werx

Legal

  • Privacy Policy
  • Terms of Service
Rivet

© 2026 Rivet, Inc. All rights reserved.