Change Order Workflow
Change Orders

Change Order Workflow

Understanding the approval, rejection, and void workflow for change orders

5 minLast updated: 2025-01-15
workflowapprovalrejectionvoidstatuspending

Change orders move through a defined workflow from creation to approval or rejection. Understanding this workflow helps you manage COs effectively and get paid for changed work.

Pro Feature

Change order management requires a Pro or Scale plan. This feature is not available on the Starter plan. Contact us at support@slpwlk.io to upgrade your subscription.

Change Order Statuses

StatusDescriptionBillable?
DraftCO being prepared, not yet submittedNo
PendingSubmitted to GC, awaiting decisionNo
ApprovedGC approved the changeYes
RejectedGC denied the changeNo
VoidedCO canceled (superseded or withdrawn)No

Draft Status

A change order starts in Draft status when you create it. In this state:

  • CO is visible only to your team
  • You can edit all fields
  • It doesn't affect contract calculations
  • You can delete it if not needed

Actions Available

  • Edit details and amounts
  • Add/remove line items
  • Attach documentation
  • Delete the draft
  • Submit for approval

Pending Status

Once submitted, the CO moves to Pending. This means it's with the GC for review and decision.

What Happens

  • GC receives and reviews the CO
  • They may request additional information
  • They may negotiate the amount
  • Clock starts for tracking response time

Cannot Edit

Pending change orders are locked for editing. If you need to modify a pending CO, you'll need to void it and create a new version.

Following Up

If a CO is pending too long:

  1. Send a polite follow-up email
  2. Reference the CO number and submission date
  3. Offer to provide additional information
  4. Document all follow-up attempts

Approved Status

When the GC approves your change order, it becomes billable and affects your contract sum.

What Changes

  • Contract sum is updated (Line 2 on G702)
  • CO work can be included in pay applications
  • Approval date and authorized signer are recorded

Recording Approval

  1. Open the pending change order
  2. Click Record Approval
  3. Enter approval date
  4. Upload signed CO document (optional)
  5. Save

Get It Signed

Always get a signed copy of the approved CO for your records. Verbal approvals should be followed up with written confirmation.

Rejected Status

If the GC denies the change order, it moves to Rejected status.

Common Rejection Reasons

  • Work considered part of original scope
  • Pricing deemed too high
  • Insufficient documentation
  • Owner/client declined the change

Handling Rejection

  1. Understand the specific reason for rejection
  2. Determine if you can address the concerns
  3. Create a revised CO if appropriate
  4. Escalate if you believe the rejection is unjustified

Voided Status

A change order can be voided when:

  • It's superseded by a revised version
  • The change is no longer needed
  • It was created in error
  • The scope was combined with another CO

Voided COs remain in the system for historical reference but don't affect calculations.

Workflow Diagram

Draft → Pending → Approved
           ↓
       Rejected
           ↓
         Void

Revision Workflow

When you need to revise a pending or rejected CO:

  1. Void the original CO (if pending)
  2. Create a new CO with revised details
  3. Reference the original CO number (e.g., "Revision of CO-003")
  4. Submit the revised CO

Notifications

RIVET can notify you of CO status changes:

  • CO approved - Ready for billing
  • CO rejected - Action needed
  • CO pending too long - Follow-up reminder

Best Practices

Track Aging

Monitor how long COs are pending. Long-pending COs often get forgotten or deprioritized by the GC.

Follow Up Promptly

If a CO is pending more than 2 weeks, follow up. Squeaky wheels get greased in construction.

Bundle Carefully

Don't put too many changes in one CO. If one item is rejected, it can delay approval of all items.

Next Steps

Learn how approved COs affect your billing.

Need Help?

If you have questions about change order workflows, contact our support team at support@slpwlk.io.

Related Articles

change ordersCreating Change OrdersHow to create and submit change orders for approvalRead morechange ordersHow COs Affect Contract SumLearn how approved change orders update your contract amount and billingRead morelien waiversSignature WorkflowRequest signatures and track lien waiver completion statusRead more
Can't find what you're looking for?
Contact Support

Product

  • Features
  • Pricing
  • Integrations

Solutions

  • For Electricians
  • For Plumbers
  • For HVAC
  • For General Trades

Company

  • About
  • Contact
  • Security

Resources

  • Support Center
  • Templates
  • Blog

Compare

  • vs Knowify
  • vs Werx

Legal

  • Privacy Policy
  • Terms of Service
Rivet

© 2026 Rivet, Inc. All rights reserved.